PROCUREMENT MANAGEMENT

Procurement Management 

Procurement management may be defined as the combined functions 
of purchasing planning, vendors qualification, purchasing, inventory 
control, traffic control, quality control, and salvage operations. 

Procurement management is a concept originally introduce by 
governments whereby the purchasing function is expanded from 
merely exchanging money for goods to one of total responsibility 
for acquiring goods. 

From the project management point of view, procurement functions 
vary according to the job progress within the project life cycle. 
Since material supply for projects is usually one of the main 
components of the total construction effort, special attention should 
be given to the functional organization that will be handling the 
procurement operation. 

Procurement during conceptual estimate paper and design basis paper,
is limited to consulting services from the engineering department 
about: 

  • Vendoravailability;
  • Marketconditions;
  • Orderofmagnitudeestimates;and
  • Deliverytimeestimates.

This consulting service is a simple but vital function considering that 
project procurement cost is usually found to be 40 to 60 percent of 
the total cost of the project. 

During Project Proposal (PP) development the main function of the 
procurement organization should be the creation of an acquisition 
schedule for long lead time materials according to the project 
milestone schedule implemented within the project execution plan. 

The acquisition schedule is usually called the Long Lead Time Material 
(LLTM) and equipment schedule and it is always a commanding 
element for the total project duration.

Additionally, during the project proposal phase preliminary materials 
take-off (TO) is carried out and a program for procurement of items 
other than LLTM is established. Materials 'take-off' (TO) is an 
engineering function that consist of reading design 
drawings and producing material and equipment schedules required 
for supporting construction of the project. 
Once the material/equipment TO's are completed, purchase 
requisitions are generated. 

Continue reading at the following internet link: https://app.box.com/s/jqx5c9qih8j3n0oydigb



.
.
 
  
  